Pipenet / AFT / Hytran software analysis — steady-state, transient, and pump-curve verification against FERA-derived demand
Firewater demand and hydraulic analysis sizes the entire firewater system — pumps, storage, ring main, distribution, hydrants, monitors, deluge headers, foam proportioning — against credible worst-case fire scenarios derived from FERA outputs. The discipline operates under NFPA 24 (private fire service mains), NFPA 20 (fire pumps), NFPA 15 (water spray for fixed protection), NFPA 22 (water storage tanks), NFPA 1142 (rural fire protection), and the insurance-grade FM Global Data Sheets (3-7, 3-26, 4-9, 7-29, 7-32). In high-hazard process industry, additional standards apply: API RP 2030 (water spray application), OISD-STD-116 (India fire protection), API STD 2510 (LPG), CEA 9 (UK), and SIGTTO terminal guidelines. Modern execution uses dedicated hydraulic modelling software — Pipenet (Sunrise Systems, dominant in oil/gas), AFT Fathom / Impulse, Hytran, KYPipe — for steady-state and transient (water-hammer) analysis. Common findings in legacy facilities cluster on inadequate ring-main looping, undersized hydrant laterals, monitor positioning that cannot reach realistic scenario radii, and the silent pump-suction NPSH problem that surfaces during full-flow demand testing. FM Global HPR qualification typically requires demonstrating 150% of largest single fire-scenario demand with single pump out of service.

Build credible-worst-case fire demand scenarios per NFPA 15/16/24 and API 2030 — single-largest-fire, two-area-simultaneous, hose-stream allowance; integrate FERA pool-fire and jet-fire footprints; calculate peak demand with monitor, deluge, foam, and hydrant loads.
Build firewater network model in PIPENET / AFT Fathom / Hydratec with node-and-element topology; specify supply (jockey, electric main, diesel backup) per NFPA 20; include underground main, post indicator valves, hydrants, deluge skids, and remote isolation.
Run steady-state hydraulic analysis under each scenario to verify residual pressure at hydraulically-remote nodes (≥1.4 barg per NFPA / FM); confirm flow-velocity envelope (≤4 m/s in mains, ≤3 m/s in branches); validate fire pump operating-point on manufacturer curve.
Conduct surge analysis for pump start-stop, deluge valve actuation, and isolation valve closure; quantify pressure transients vs pipe pressure rating; specify surge mitigation (surge tanks, air vessels, slow-closing valves) where transient envelope exceeds 1.5× steady-state.
Size fire pump (electric + diesel backup) per NFPA 20 with 150% rated-flow / 65% shut-off curve check; size firewater storage for credible-worst-case scenario duration (typically 4-hour per NFPA / FM); verify suction-lift / NPSHa under all conditions.
Issue firewater network design basis, hydraulic calculation report, pump curve sheets, storage sizing, and surge analysis; specify NFPA 25 ITM procedure with weekly / monthly / annual frequency; provide commissioning flow-test protocols and acceptance criteria.

Complete Firewater Hydraulic Modelling & Demand Calculation scope — every calculation, drawing, specification, and construction support activity.
Speak with our team to scope an engagement tailored to your facility, regulatory context, and lifecycle stage.